Your Customer wants your project, to be completed 5 months earlier than planned. You believe that you can meet the target by overlapping the project activities. The approach you plan to use is known as:

2 votes
A. Crashing
 
50% / 1 vote
B. Resource Levelling
 
0% / 0 votes
C. Resourcer
 
0% / 0 votes
D. Fast Tracking
 
50% / 1 vote